Pacgold ramps up South Australian gold production with second pour
Brought to you by BULLS AND BEARS
Andrew Todd
Pacgold has doubled down on its new producer status by pouring a second doré gold bullion from its White Dam project in South Australia as it plans to accelerate the restart of open-pit mining at the project six months ahead of schedule.
The company says it delivered a 97-ounce gold bar from the first vent of the former heap leach site.
The spill comes as management announced it was considering an early restart of the nearby Vertigo open pit; This could enable fresh oxide gold ore to hit the leach field in late 2026 rather than mid-2027.
The move to accelerate Vertigo was recently triggered by additional shallow, high-grade gold strikes from drilling beyond the existing open-pit shell.
‘It is also excellent news to confirm that the re-broken material now achieves good qualities in the top lift.’
Matthew Boyes, managing director of Pacgold Ltd
The company said the 97-ounce player validates the operational increase at White Dam, which Pacgold only acquired late last year.
The company’s recrushing campaign is now making major progress, with 120,000 tonnes of material from the existing pile being crushed and irrigated. It is planned to add another 50,000 tons by the end of the month.
Significantly, management says, high-grade leachate has now reached the base of the refractured material. Although this newly leached gold has not yet reached the processing plant, its presence at the bottom of the system is a strong indication that the refraction strategy is effectively releasing trapped gold and bodes well for future production ounces.
While gold has retreated from its January peak due to declining inflation fears and a strong US dollar, major investment institutions, including Goldman Sachs and JP Morgan, maintain their target of US$ 4900-5000 per ounce for 2026.
As the recrushing program continues to generate cash flow in the short term, all eyes now turn to the Vertigo pit, where Pacgold is processing fresh oxide ore from the northern and eastern edges of the pit.
Since the existing heap leach field has a reserve capacity of 800,000 tonnes, mining can be carried out without additional permits or capital expenditure.
Pacgold managing director Matthew Boyes said: “The delivery of our second gold pour from White Dam provides additional cash flow as production increases; confirmation that the refractured material is now achieving good grades at top lift is excellent news and I look forward to this leachate reaching the site to be recovered in future castings.”
Pacgold expects White Dam to return to its proven historical gold production, having recovered 180,000 ounces of gold from heap leach operations between 2010 and 2018.
The current resource of 4.6 million tonnes grading 0.7 grams per tonne (g/t) gold for 102,000 ounces provides a solid platform for the potential restart of production, even if recently identified shallow gold ounces are not included.
While the current ore reprocessing process is expected to deliver gold production in the short term, Pacgold’s broader goal is to return White Dam to full-scale mining.
The company said a cost-effective pathway to restart mining, including economic studies, is expected within the next two to three weeks, followed by permit applications and contractor engagement.
Consultant Entech was also hired to update the Vertigo mine resource estimate and conduct new pit optimizations for mine designs to support the early restart plan.
The project’s long-term plan includes a massive 4 million tonne expansion of the heap leach pad to accommodate ore from the company’s Vertigo, White Dam North and Hannaford deposits.
Pacgold, who transitioned from explorer to producer with his first gold strike last month, is wasting no time in gaining momentum. With the second bar filled, the recrushing campaign gaining traction and a clear plan to accelerate open-pit mining, White Dam appears to be rapidly transforming from a historic producer to a modern-day cash machine.
Is your ASX-listed company doing something interesting? Contact: mattbirney@bullsnbears.com.au